 Europe's Vega
Smallsat LauncherEurope's new Vega
launch vehicle flew for the first time on February 13, 2012, achieving a flawless
inaugural mission. The small launcher lifted off at 10:00 UTC from the former ELA 1
pad, rebuilt as the Vega Launch Site (ZLV: Zone de Lancement Vega) at the Guiana Space
Centre, in Kourou, French Guiana. Flying the VV01 mission for the European Space
Agency (ESA), Vega orbited two scientific satellites and seven picosatellites. These
included Italys 400 kg LARES laser relativity satellite, the 12.5 kg ALMASat-1
technology microsatellite demonstrator from the University of Bologne, and seven 1kg
university CubeSats.
Vega is powered by three solid propellant stages and a
liquid-propellant fourth stage. The P80FW first stage, roughly speaking, corresponds
to one segment of the standard P230 Ariane 5 booster, but is only loaded with 88.365
tonnes of HTPB propellant. A P230 uses two 100 tonne segments and one 30 tonne
segment. In addition, P80FW uses a carbon-epoxy
filament-wound motor casing rather than the steel casing used by P230.
The Zefiro-Z23 second stage and Zefiro-Z9A third stage
were developed in Italy for Vega. Vegas liquid fourth stage, the restartable,
hypergolic bipropellant Attitude and Vernier Upper Module (AVUM), is powered by a 250 kgf
Ukranian RD-869 engine. AVUM is loaded with 550 kg of UDMH/NTO propellant in four
tanks. Vega is topped by a 2.6 meter diameter payload fairing.
The four-stage rocket is designed to inject
1,500 kg into a 700 km x 90 deg polar orbit. Vega weighed 136.7 tonnes at liftoff
and stood 30.1 meters with a maximum diameter of 3 meters.
During the VV01 mission, AVUM performed
three burns. The first burn trimmed the vehicle into a transfer orbit. After a
40 minute coast, the second burn pushed the stage into a 1,450 km x 69.5 deg circular
orbit, where it released LARES. AVUM then fired again to reduce the perigee to 350
km before deploying the other payloads.
The
four-stage small/medium payload launcher was jointly developed by the Italian Space Agency
and the European Space Agency (ESA). ELV S.p.A., a joint venture of Italys AVIO
S.p.A. and the Italian Space Agency (ASI), is the Vega prime contractor.
Background
Although the commercial communication
satellites launched by Europes Arianespace launchers have grown larger and heavier,
scientific and Earth observation satellites have tended to remain relatively light,
weighing in at two tonnes or less. Scientific
satellites also tend to use polar or other orbits not used by geosynchronous satellites,
minimizing chances for shared flights. Vega was designed to fly such smaller
payloads economically by lifting a reference 1.5 metric tonne payload into a 700 km polar
orbit.
Although proposed to become a European
project by the Italian Space Agency in 1998, Vega did not win ESA approval until December
2000. In its final form, the project was
reshaped to provide spin-off improvements for the Ariane 5 solid rocket booster. Improvements include the development of a graphite
epoxy filament wound case to replace the existing steel casing, an electromechanical
thrust vector control system, and a carbon phenolic nozzle.
A modified composite propellant formula, HTPB 1912, was also selected. Vegas Zefiro motors were also to employ
graphite epoxy filament wound casings.
Development funding totaled nearly
$400 million by some accounts. Italy provided
65% of the total. France provided more than
12%. Belgium, The Netherlands, Switzerland,
and Sweden together funded the remainder.
Vegas target launch price was
about $23.5 million, less than comparable U.S. launchers but substantially more than Russias
comparable Rokot/Briz. Like many government
funded launch programs, the price will not necessarily correspond to the actual cost of
the launcher. ESA governments agreed to
provide nearly $290 million of subsidies to the Vega program during its initial five
launches. By agreement, the launch price will remain
fixed for several years.
The Design
Vega consists of three solid rocket
stages topped by a liquid fourth stage. The
310 tonne thrust P80 first stage is derived from a single segment of the Ariane 5 strap-on
booster. The second stage is a 122 tonne
thrust Zefiro 23. Stage Three is a 32 tonne
thrust Zefiro 9. All three stages are equipped with
flexible nozzles and to control vehicle pitch and yaw during their burns.
The fourth stage, named Attitude
and Vernier Module (AVUM), is equipped with a low-thrust liquid hypergolic
propulsion system. The AVUM stage provides
roll control during some of the solid rocket stage burns, attitude control during coast
periods, circularization burns when needed, and final velocity trim. Vega avionics, which are derived from Ariane 5 systems,
will be located on the AVUM stage.Vega stands 30 meters tall, has a maximum 3-meter
diameter, and weighs about 137 tonnes at liftoff. The
launcher flies from Kourou Space Centers ZLV (Zone de Lancement Vega) launch site,
a rebuilding of Kourou's ELA 1 pad. ELA 1 once
handled Europa 2 and Ariane 1. Arianespace will conduct Vega launch campaigns. Vegas initial qualification flight is
expected to be followed by two to four operational launches per year.
Development Progress
Vega endured a stop-start development
effort during the 1990s. Original plans called
for use of a standard Ariane 5 booster steel-case segment for the Vega first stage. The second stage would have been a Zefiro 16 (16
tonnes propellant) second stage. The third
stage would have been loaded with seven tonnes of propellant. The original Vega would only have been able to
boost one-tonne payloads to polar orbit.
Italy initially pressed Vega
development forward, performing a Zefiro 16 static test on June 18, 1998. The effort stalled after that, however, when France
balked at fully participating in the project. The
Vega design was subsequently modified both to carry larger payloads and to serve as an
Ariane 5 solid rocket booster improvement program.
When Vega won ESA approval in December
2000, development had to be reset. Initial
plans called for an initial test flight by the end of 2005.
Vegas preliminary design review occurred in mid-2001, but the Critical
Design Review did not occur until March 2004, a delay of nearly nine months from original
plans. By late 2006, the program schedule had
slipped by nearly two years from original plans, largely due to funding issues.
Avio
S.p.A. completed testing of the Vega solid rocket motor igniters by September 2005. The first Zefiro 9 qualification test burn took
place in Sardinia, Italy on December 20, 2005. A second,
unsuccessful test took place on 28 March 2007. During the 2007 test, motor pressure
unexpectedly dropped after 35 seconds. Zefiro 9A motors with a modified nozzle
designs were successfully tested on October 23, 2008 and April 28, 2009.
The Zefiro 23 qualification test occurred at
the same site on June 26, 2006. A second Zefiro 23 test took place on March 27,
2008.
P80 was test fired at Kourou on November 39,
2006 and December 4, 2007. The tests demonstrated the motors ability to produce 190
tonnes of average thrust for 111 seconds.
Europropulsion cast the first inert P80 Vega casing for Avio S.p.A. at the
Guiana Propellant Plant (UPG) at Kourou during April 2004. By mid-2006, Europropulsion had
cast propellant for the first P80 static qualification test firing article. Snecma in
Bordeaux, France delivered the P80 motor nozzle during September 2006. The first P80
static test firing, of the DM1 demonstration motor, occurred at Kourou's vertical solid
booster test stand (BEAP) on November 30, 2006.
In September 2006, the AVUM module
completed vibration testing at the European Space Research and Technical Center in The
Netherlands.
An additional round of solid motor
static tests for all three Vega stages took place during and after 2007.
Launch Site
ZLV, The old ELA 1 launch zone, hosts
Vega. ELA 1 was originally built for Europa 2,
which flew only one time in 1971. The pad was
subsequently modified for Ariane 1, which it hosted from 1979 until 1989. The sites mobile service tower was
dismantled in 1991.
Vega launch site construction began in
late 2004 and continued beyond the end of 2008. Beginning in October 2010, ZLV
hosted the buildup of a pathfinder mockup Vega vehicle that was used for a dry run to test
facilities and procedures until April 2011. A few months later, ZLV began to support
the VV001 launch campaign.
The rebuilt launch site includes a
fixed launch table atop a launch bunker fitted with exhaust ducts and a fixed
umbilical tower. A new mobile gantry,
essentially a vertical building on wheels, serves as the assembly building for the
launcher and payload. Four lightning towers
straddle the launch site. Vega launch control
is performed from Kourous Launch Control Center No. 3 (CDL3) building, which also
controls Ariane 5 launches.
Vehicle Configurations
| |
LEO
Payload
(metric tons)
(1) 300 km x 0 deg
(2) 700 km x 90 deg
(3) 1500 km x 90 deg |
Configuration |
LIftoff
Height
(meters) |
Liftoff
Mass
(metric tons) |
Price (2005)
$Millions
|
| Vega |
2.3 t (1)
1.5 t (2)
1.1 t (3) |
P80 + Zefiro23 + Zefiro9 +
AVUM + PLF |
30.1 m |
136.7 t |
$23.5 m
|
Vehicle Components
| |
Stage 1
P80FW |
Stage 2
Zefiro 23 |
Stage 3
Zefiro 9A |
Stage
4
AVUM |
Payload
Composite |
| Diameter (m) |
3.0 m |
1.9 m |
1.9 m |
1.9 m |
2.6 m |
| Length (m) |
11.2 m |
8.39 m |
3.85 m |
1.74 m |
7.18 m |
Empty Mass (tonnes)
|
8.65 t |
1.9 t |
0.78 t |
t |
0.47 t |
| Propellant Mass (tonnes) |
88.365 t |
23.9 t |
10.115 t |
0.55 t |
|
| Total Mass (tonnes) |
97.015 |
25.8 t |
10.9 t |
t |
|
| Engine |
P80FW |
Zefiro 23 |
Zefiro 9A |
RD-869 |
|
| Mfgr |
Avio |
Avio |
Avio |
YB Yuzhnoye
Avio |
Oerlikon
Contraves |
| Propellant |
HTPB 1912 |
HTPB 1912 |
HTPB 1912 |
UDMH/NTO |
|
Thrust
(SL tons) |
230.56 t |
t |
t |
t |
|
Thrust
(Vac tons) |
310 t |
121.96 t |
31.92 t |
0.25 t |
|
| ISP (SL sec) |
s |
s |
s |
s |
|
| ISP (Vac sec) |
279.5 s |
289 s |
294 s |
315.2 s |
|
| Burn Time (sec) |
114.3 s |
86.7 s |
128.6 s |
s |
|
| No. Engines/Motors |
1 |
1 |
1 |
1 |
|
Comments
|
|
|
|
|
|
References
"The Small Launcher for Europe", ESA Vega
Overview, November 2005
Vega Qualification Flight VV01 Press Kit, ESA, February 2012
Last Update: February 22, 2012
by: Ed Kyle |